BTS Navigation Bar

NTL Menu


Management of Urban Construction Programs




           MANAGEMENT OF URBAN CONSTRUCTION  PROGRAMS

                    National Research Council
              Commission on Sociotechnical Systems
                Building Research Advisory Board
                  Committee on Management of Urban
                        Construction Programs
                  2101 Constitution Avenue, N.W.
                       Washington DC 20418









                         Click HERE for graphic.




                              JUNE 1981
                            FINAL REPORT

                DOCUMENT IS AVAILABLE TO THE PUBLIC
                  THROUGH THE NATIONAL TECHNICAL
                 INFORMATION SERVICE  SPRINGFIELD
                            VIRGINIA 22161









                            Prepared for
                  U.S. DEPARTMENT OF TRANSPORTATION
             URBAN MASS TRANSPORTATION ADMINISTRATION
           Office of Technology Development and Deployment
             Office of Rail and Construction Technology
                          Washington DC 20590


PREFACE

        This report was prepared by the Building Research
Advisory Board (BRAB) Committee on Management of Urban
Construction Programs under Contract No. DOT-TSC-1728 managed
by the Transportation Systems Center (TSC), Cambridge,
Massachusetts. The contract is part of a program sponsored by
the Office of Rail and Construction Technology, Office of
Technology Development and Deployment, Urban Mass
Transportation Administration (UMTA) of the U.S. Department of
Transportation.

        The overall objective of this contract is to develop
guidelines that can be used by local governmental authorities
in developing sound management plans for the execution of
federally funded urban construction projects.  The report
presents the guidelines from the perspective of the project
manager since this position carries the responsibilities for
design and construction of a project and, possibly,
for activation and operation of a facility or system.

        The guidance and suggestions of Mr. Paul Witkiewicz of
the Transportation Systems Center, technical monitor, and of
Mr. Gilbert Butler of the Urban Mass Transportation
Administration, program manager during the study effort were
greatly appreciated.

iii


                         BRAB COMMITTEE
              MANAGEMENT OF URBAN CONSTRUCTION PROGRAMS


Chairman

SAMUEL L. HACK, Management Consultant, Washington, D.C.

Members

WILLIAM D. ALEXANDER, Consultant, Pawleys Island, South
     Carolina
FRANK HANLEY, General Vice President, International Union of
    Operating Engineers,        Washington, D.C.
JAMES A. LILLY, Executive Vice President, Morrison-Knudsen
    Company, Inc., Boise, Idaho
R.M. MONTI, Chief Engineer, The Port Authority of New York and
    New  Jersey, New York, New York
O'ROURKE, Assistant Professor of Civil Engineering, Cornell
    University, Ithaca, New York
RICHARD S. PAGE, General Manager, Washington Metropolitan Area
    Transit Authority,  Washington, D.C.
LOUIS W. RIGGS, FASCE, President and Director, Tudor
    Engineering Company, San Francisco, California
ROBERT A. RUBIN, Esq., PE, Partner, Postner and Rubin, New
     York, New York

Liaison

WILLIAM CULLEN, Vice President, Johnson and Higgins, New York,
New York

BRAB Staff

JOAN D. FINCH, Staff Officer
EVAN ANDERSON, Consultant
CLARET M. HEIDER, Editorial Consultant
BARBARA J. BISHOP, Secretary



DOT Staff
PAUL WITKIEWICZ, Civil Engineer, Transportation Systems Center
GILBERT BUTLER, Program Manager, Urban Rail and Construction
Technology, UMTA

v/vi


                         TABLE OF CONTENTS

I.   INTRODUCTION                                          1

     Purpose and Scope of Report                           2
     Conduct of the Study                                  3

II.  PURPOSE OF A PROJECT MANAGEMENT PLAN                  5
III. CONTENTS OF MANAGEMENT PLAN FOR URBAN CONSTRUCTION
                PROGRAMS                                   7

     A. Parameters and Constraints                         7
        1. Project Description                             8
        2. Legal Authority and Requirements                8

     B. Organization and Staffing                          9
     C. Management Control Systems                        10

        1. Functional and Technical Control               10
        2. Cost Control                                   11
        3. Schedule Control                               12
        4. Financial Receipts and Disbursements           12
        5. Change Control                                 13

     D. Human Resources and Labor Relations Policy        13

        1. Statutory and Regulatory Requirements          13
        2. Labor Relation                                 13
        3. Local Conditions                               14

      E. Risk Management                                  14

      F. Dispute Resolution                               14

      G. Procurement                                      15

         1. Policy and Procedures                         15
         2. Negotiation and Administration                15
         3. Procurement Plan                              15

      H. Design Program                                   15

ix


     I. Real Estate Acquisition and Disposal Program      15

     J. Communications Program                            16

     K. Construction Program                              16

     L. Legal Requirements                                16

        1. Permits                                        16
        2. Approvals                                      16
        3. Disputes Resolutions                           16

     M. Safety Program                                    16

     N. Operation and Maintenance Interface               17

     O. Communication Interface Management                17

     P. Maintenance of the Plan                           17


APPENDIX                                                  19

REFERENCES                                                21

x


FOREWORD



The management of large-scale public works projects is an
increasingly important issue.  The major investment of public
funds in such projects requires a comprehensive management plan
that covers all aspects of a project from initial conception,
through the political, financial, design and construction
stages, and into actual operation.  It is, however,
particularly difficult for local governments to assemble the
management and engineering capability needed to handle such
projects.  The work of the BRAB Committee on Management of
Urban Construction Programs is specifically oriented toward
providing these local entities with a guide that will help them
carry out this important and complex function.


                                 Joseph H.Zettel, Chairman
                               Building Research Advisory board

vii/viii


                                 I
                            INTRODUCTION




The increasingly critical situation arising from failure to
deal effectively with inherent risks in construction prompted
the Building Research Advisory Board (BRAB), with the support
of the U.S. Department of Transportation, to conduct an
exploratory study of responsibility, liability, and
accountability for risks in construction. Of principal concern,
particularly on large-scale public works projects, were rapidly
escalating costs and delays in providing or actual denial of
vital public services.  A series of workshops, one of which was
devoted to urban and suburban mass transit construction, and a
conference were held to identify problems and potential solutions.

                The BRAB Committee responsible for this
exploratory study identified the administration and management
of the construction process as an area in which major problems
arise concerning responsibility, liability, and accountability
for risks.  In it's final report (Exploratory Study on
Responsibility, Liability, and Accountability for Risks in
Construction, 1978), the Committee concluded:


    Delays that cannot be known or predicted adequately result
  in the greatest losses to all parties to the construction
  process but most particularly to the owner and the general
  public.  Even predictable delays have a serious impact on the
  sequencing and efficiency of project execution.

    A lack of understanding of authority and responsibility and
  a lack of coordination and communication generally exist
  among the parties to the construction process.  These
  differences together with an adversarial relationship that
  often exists among the parties cause ambiguity or inequity in
  allocation of liability and increase the likelihood of costs
  in disputes.  Delay and losses due to cost escalation and
  reduced productivity and beneficial use of a facility also
  may result.

The Committee recommended that:

    Decision-making roles at a11 levels in the construction
  process should be identified and defined and the requisite
  responsibility

1


  and authority should be assigned in order to improve the
  badly disjointed decision-making process that now exists. . .
  . Mechanism that will provide better communication and
  development of the team approach among all parties to the
  process should be explored in order to further minimize
  escalating adversary relationships.

        The increasing size and complexity of many public
service projects and the involvement of federal, state, and
local governmental grant and regulatory agencies complicate
management of the delivery process.  Recently developed methods
of designing and constructing major urban construction projects
and the actions of governmental and nongovernmental public
groups have further complicated the process.
        Sound management practices, communicated to all
participants in the construction process, are essential if the
concurrent activities in the process are to be controlled,
performance is to be evaluated and measured, and corresponding
benefits in time and cost are to be achieved.  However, every
major construction project is unique, occurring in a specific
locale with specific people participating in the process, and
no one management plan can be used by all agencies or in all
situations.  Nevertheless, the primary elements necessary
to sound management plans can be identified.
        Stimulated by the conclusions and recommendations
reached in the BRAB exploratory study, the U.S. Department of
Transportation's, Urban Mass Transportation Administration
requested that BRAB undertake a study of management of urban
construction programs to develop guidance that could be used by
local governmental authorities in developing sound management
plans for the execution of federally funded urban construction
projects.  The results of this study are the subject of this
report.

A. PURPOSE AND SCOPE OF REPORT

This report of the BRAB Committee on Management of Urban
Construction Programs is intended to guide local authorities
(such as transportation, water, and sanitary agencies) in
developing management plans for executing urban construction
projects.
        The guidance presented has been developed from the
perspective of the "project manager."  Because of the unique
aspects of every major construction project, it is not possible
to define exactly the function and full responsibility and
authority vested in the project manager position; however, it
is assumed that the position carries responsibility for design
and construction of a project and, possibly, for activation and
operation of a facility or system.  The conceptual planning
phase of a project, during which needs, conceptual contentions,
social and environmental impacts and local political acceptance
are evaluated, is not covered in detail since the results of
this phase are taken as givens for the project management plan.

2


B. CONDUCT OF THE STUDY

   The BRAB Committee on Management of Urban Construction
   Programs was charged with developing a report setting forth
   the Committee's guidance concerning:

        a. Developing project management for planning and
           executing urban construction projects;

        b. Assigning responsibility, authority, and control in
           the decision-making process;

        c. Developing the communication mechanisms and
           documentation required for implementation of
           management of construction; and

        d. Identifying procedures for initiating and developing
           management plans for urban construction projects.

        The Committee conducted an informal survey to review
        management guidelines and procedures for executing
        construction projects that have been developed by both
        public and private organizations.  Included in this
        survey were 17 local transportation authorities that
        were asked whether they had a formal management plan for
        executing urban construction projects.  If they did,
        they were asked to submit a copy and explain when it
        was instituted and how staff members and other project
        participants were familiarized with it.  If they did not
        have a formal plan, they were asked to submit copies of
        memos, reports, or other documents used to execute
        construction projects.  In addition, they were asked to
        submit an organization chart, if available, that would
        show the organizational structure and staffing of the
        authority, how construction activity related to the
        overall structure, and how responsibility and authority
        were delegated among the various personnel.

3/4


                                 II
                 PURPOSE OF A PROJECT MANAGEMENT PLAN

The planning of an urban construction project requires an
extensive conceptual planning phase that includes studies of
needs, demographics, economics, social and environmental
impacts, financing, and public and political support.  These
studies should result in a general description of the project
and the budget and schedule for its completion.  Only if they
are realistically interrelated can these studies serve as a
measure of the successful execution of a project.  There also
must be a management plan covering execution of the project.  A
written project management plan sets forth the implementation
strategy and serves as an interface document between the
conceptual planning and project execution phases.

        A written project management plan serves a multitude of
management purposes. Initially, it demonstrates that the owner
has analyzed the management and execution needs for a project
and has considered the methods to be used and the interface
problems that will be created among the various participants.
A written plan also is a mechanism for communicating the
objectives of a project to all project participants (including
those whose interests or roles are outside the direct
performance of the project) and the methods and resources
proposed to be used in meeting these objectives.  For
participants directly involved, it communicates the overall
management strategy and the responsibilities, authorities, and
types of mechanisms or procedures that will be used to which
their portion of the project must adhere.  To participants not
directly involved, it provides information to assist in
assessing the project's impact on their interests and the
appropriate interface with the project to represent their
interests.  A well-organized plan also will give an indication
of the probability of a project's success.  It also must be
recognized and remembered that the plan establishes for the
owner those standards on which he will measure total project
performance.

        A written plan assists in the creation and maintenance
of a team approach. A coordinated effort to meeting the project
objectives is essential for executing a major project in a timely
and efficient manner.  As in all team efforts, each  participant
must know his role and the role of the others and there must be
a leader. During project execution, important decisions must be
made and problems are to be expected even though the exact
nature of problems cannot be predicted.

5



Decisions not made and problems not resolved in a timely manner
cause delays and tend to stimulate adversary relationships that
are destructive to the team approach.  Thus, a written project
management plan identifies procedures for timely resolution of
problems and assigns authority.

        It is important that a written plan be as concise as
possible, keeping in mind the purposes being served.  Detailed
procedures and standards can be included in appendixes or
referenced documents with their function in the management
scheme set forth in the actual plan.

        A management plan emphasizes the unique character of a
project because even projects that are seemingly alike vary in
scope, location, and participants. A plan also must be a vital,
current, and progressive management tool.  It should be revised
or expanded in coverage when revised execution strategies are
indicated, participants are added, or design development or
permit restrictions create unforeseen needs.

       The limitations of a project management plan also should
be noted.  A plan is not a self-executing document, and a
competent, experienced staff at all levels, working as a team
to reach a common objective, is essential for successful
execution of the project.  In addition, regardless of how
well-developed a plan may be, factors outside the control of
project management--such as delayed funding, political inaction
or dissension, injunctive work stoppages, and public
actions--can create schedule delays and cost increases.

6


                        III
 CONTENTS OF MANAGEMENT PLAN FOR URBAN CONSTRUCTION PROGRAMS




   The guidance given below for developing a project management
   plan is intended primarily to identify parameters and
   constraints and elements that should be considered for
   inclusion.  Neither the sequence nor the grouping of items
   given below should constrain the developer of a management
   plan from selecting an arrangement that will better meet his
   needs to communicate information to project participants.
   No detailed guidance for developing and executing any
   portion of a management plan is included because a variety
   of options may be available for any given project; however,
   alternative choices and examples of practices and procedures
   that have been used are given in Volume 2 of this report.
        Some decisions may affect many elements of a plan and
   should be made prior to extensive efforts to develop a plan.
   These decisions may relate to such factors as: (1) the
   structure of and legal authority vested in the responsible
   local agency in relation to other local and state agencies,
   (2) the extent to which existing agency staff is to be used
   or new staff is to be developed, and (3) local
   considerations relating to labor and economic conditions.

A. PARAMETERS AND CONSTRAINTS

   The guidance presented in this report does not cover the
   conceptual planning phase for a project during which needs,
   conceptual contentions, social and environmental impacts,
   and local acceptance are evaluated.  However, the importance
   of this phase and how it interfaces with the project
   management plan must be recognized since the plan serve as
   the essential link between conceptual planning and project
   execution.

       During the conceptual planning phase for a project,
   certain parameters are established that must be recognized
   and considered as the scope and limitations of the
   environment within which the project will be executed.
   These parameters serve as the general basis on which the
   project was authorized for funding and implementation.  In
   addition, the legal considerations that will constrain the
   environment within which the project is to be developed and
   executed must be recognized and communicated should any of
   these "givens" be altered

7


   during the course  of the project, the management plan may
   have to be adjusted accordingly.  The products described
   below are normally developed during the conceptual planning
   phase and should be included in the written project
   management plan.

  1. Project Description

     The narrative description of the project should include a
     physical description of the project and a discussion of
     those aspects of the project's history and background that
     will contribute to understanding of the project’s
     objectives and management strategies.  Those aspects of
     other projects that are dependent on or supportive of
     activities covered by the management plan also should be
     described.  Also included should be a description of those
     portions of project planning, financing, design,
     acquisition (e.g., real estate, services, materials,
     equipment,), permitting, licensing, construction, and
     operations covered by the plan and the status of the
     project at the time the plan is issued.

     a. Physical Description and Function

        System components should be described in terms of
        physical and functional requirements and overall design
        criteria.  The conceptual design developed in the
        conceptual planning phase should set forth the intended
        performance characteristics of the completed project.

     b. Budget

        Budget estimates should be provided for the overall
        project and should be broken down by major physical
        components and/or functions in accordance with the
        project physical description developed during the
        conceptual planning phase.

     C. Schedule

        A projected schedule for project completion should be
        provided giving target dates for completion of major
        system components and/or functions, and all major
        milestone events (e.g., those that may relate to
        critical functions or funding requirements) should be
        identified.

  2. Legal Authority and Requirements

     All applicable legal constraints must be clearly
     recognized by the persons formulating, evaluating, and
     implementing a project management plan.  These constraints
     will apply to individual program components but should be
     set forth collectively.

     a. Statutory Authority

       The authority and requirements for real estate
       acquisition (including condemnation), local financing,
       procurement, and implementation of the project should be
       identified.
8


     b. Regulations

        Key government  regulation that must be adhered to
        (e.g., environmental, health and safety, civil rights,
        codes, and ordinances) should be identified.

     c. Existing Governmental Structure

        All authorities having power over decision-making,
        approvals, and the issuance of permits or licenses with
        which channels of communication and a working
        relationship will have to be established (e.g.,
        building, planning, fire, health, public works and
        transportation departments) should be identified.

B. ORGANIZATION AND STAFFING

   Organizational arrangements are highly dependent on the
   decision made concerning use of in-house staff or outside
   organizations.  The size, qualifications, and availability of
   existing staff must be considered.  The desirability of
   developing an adequate in-house staff depends on the range
   and level of expertise needed, the duration of need
   (including the operational phase), the costs, the amount of
   control needed, the diversity of experience that can be
   brought to bear, and the time available to develop a working
   team.  Even when an outside organization is used, the owner
   must have an organization to maintain overall control of the
   project, to provide for timely decision-making that must
   come from the owner, and to maintain appropriate
   communication channels to all participants. Needless to say,
   any organizational arrangement that would result in
   duplication of effort or that would tend to undermine
   authority should be avoided.
        An owner may elect to procure project management,
   design, construction management, construction, legal,
   inspection, and data processing services from outside
   sources.  Those portions of the project for which existing
   staff participants will be responsible and those portions
   for which outside services will be sought should be
   identified clearly in the scope of work assigned to
   participants.
        The main organization and staffing functions are
   outlined in this report as separate elements; however, these
   functions can be combined or responsibilities can be shifted
   among organizational units depending on the experience and
   capabilities of the individuals and organizations that are
   available to carry out the functions identified.
        The organization and staffing elements of the project plan
   should be developed along the following lines:
        1. Project organization charts showing the complete
   organization  should be developed and should cover all
   project functions and all project personnel, regardless of
   affiliation.  Staffing levels should be indicated.  Charts
   may be time-oriented to show different organizational
   arrangements if these will be changed for different phases
   of the project.
        2. Key personnel in a11 organizations should be
   identified and their principal duties, reporting
   relationships, and assigned responsibility and delegated
   authority should be defined.

9


        3. Interface points within and outside the project
   organization should be identified.
        4. Company organization charts showing the
   organizational placement of personnel assigned to the project
   and the interface points with the project should be required
   for all major companies participating.
        5. A staff mobilization plan that incorporates a
   schedule of milestone events should be developed.
        6. The philosophy that governs the development of the
    project organization should be stated and decisions to
    contract for or use in-house services should be explained.


C. MANAGEMENT CONTROL SYSTEMS

   Three elements are essential in every project: quality,cost,
   and schedule.  All are variables, and if one element is
   changed in some way, the others are affected.  It is
   therefore essential that the initial assumptions (baselines)
   be identified and controlled.
        A major work breakdown structure (WBS) should be
   prepared to serve as the basis on which work is divided into
  work packages that must be manageable and should be managed.
   A WBS normally is prepared in an hierarchical or multitiered
   fashion with the lower tiers being defined during design and
   project execution.  However, the WBS should be developed to
   best suit project management purposes, not those of the
   control or information system specialties.  The WBS should
   be used as the basis for technical, cost, and schedule
   control; therefore, the packages of the WBS and their
   assigned costs and schedules must be entirely consistent
   with the overall physical and functional project
   description, cost estimate, and schedule.  All work packages
   must be identified in both the estimate and the schedule.
        The use of logic or network diagrams can be a valuable
   tool in developing the management plan.  This tool, which
   can display graphically the intent of the plan, will
   highlight critical areas that must be dealt with in the plan
   (e.g., critical decisions, potential conflicts, and
   restraints).   Simple activity-oriented network diagrams
   (using the major  work packages) can define the project
   scope and reflect the interdependencies among various
   design, procurement and construction activities, the phases
   of work, and the impact of outside work groups.  The network
   diagrams should reflect all  facets of the project from
   authorization to operation of the facility or system.

   1. Functional and Technical Control

     a. Technical Baseline

        Responsibility should be assigned for providing clear
        design criteria and required quality and other
        standards to those performing design and for
        coordinating individual design packages with system-
        wide design.  The authority to make changes or waive
        requirements also should be identified.

10


     b. Design Review

        Responsibility should be assigned for providing for and
        coordinating design reviews by the owner, consultants,
        and operational staff to assure that project objectives
        are being met.  During design review, attention should
        be directed to consistency with design criteria,
        possible errors and omissions, and constructability.
        Determining the extent of review or multiple reviews
        required should be based on consideration of the
        consequences of failure, the owner's experience with
        the design organization's in-house checking capability,
        and other aspects of the quality assurance programs.

     c. Quality Assurance Program

        Responsibility should be assigned for establishing and
        implementing individual and organizational quality
        assurance (QA) programs to provide an effective system
        for ensuring that: (1) all work performed is in
        accordance with engineering requirements; (2) all
        equipment is tested throughout development,
        manufacture,and installation to verify that it will
        function as specified; (3) undesirable conditions are
        detected early and positive corrective action is taken
        in a timely manner; and (4) control over the system
        hardware configuration is maintained at all times to
        define the acceptability of equipment (as established
        by design reviews, drawing approvals, and design
        verification testing), to control the configuration
        during retrofits and modification work, and to ensure
        that the system  will be safe for public use.
                The QA programs should meet the stated
        objectives and should provide for documentation to
        support such requirements as contractor quality
        assurance, management quality assurance audit,
        surveillance of contractor work, and testing and
        configuration control.

     2. Cost Control
        a. Cost Baseline

           Responsibility should be assigned for developing a
           baseline costs budget for managers of work packages
           and for maintaining that baseline consistent with
           the WBS, schedule, and overall costs.  Authority to
           revise the baseline should be identified.

        b. Performance Measurement

           A system should be provided for comparing the actual
           costs to the planned costs of elements of work and
           for analyzing any variances from the planned costs
           that may occur.

        c. Cost Forecast and Estimate Reviews

           A system should be provided for routinely
           forecasting the expected costs of work packages at
           completion and of the total

11


           project.  In addition to routine cost forecasting,
           as design develops and contracts for materials,
           equipment and services are awarded, provision should
           be made for periodic reviews and updates (conducted
           from an overall management perspective and
           preferably on a quarterly or semiannual basis) of
           the systemwide estimate.  Elements of the project
           cost estimate should be subject to varying degrees
           of re-estimating depending on the status of project
           development, changes in previously predicted
           economic conditions, unfavorable experience in
           contract awards, or refinement of quantities.
           Project management should determine the degree to
           which re-estimating is to be performed, recognizing
           its cost and the extent to which it will interfere
           with ongoing performance.  Schedule impacts should
           be considered in conjunction with these periodic
           cost estimate reviews.


        d. Contingency Management

           A system should be provided for determining and
           distributing contingency funds to provide for cost
           escalation caused by such factors as inflation,
           changed conditions, design revision, and estimating
           errors.  The contingency allowances can be held at
           the project level or can be distributed to lower
           levels of management in the WBS.

     3. Schedule Control

        a. Schedule Baseline

           Responsibility should be assigned for developing
           baseline schedules for the managers of work packages
           and for maintaining those baselines consistent with
           the technical, cost, and overall schedule baselines.
           Authority to revise the baselines should be
           identified.

        b. Performance Measurement

           A system should be provided for comparing actual
           work performed with the scheduled work to be
           performed and for analyzing any variances  that may
           occur.

        c. Schedule Forecast and Review

           A system should be provided for routinely
           forecasting the expected schedule for completion of
           work packages and the total project.  Schedules
           should be reviewed and updated in conjunction with
           the periodic cost estimate reviews.

     4. Financial-Receipts and Disbursements

        A system should be established and responsibility
        assigned for predicting cash flow requirements and for
        providing for timely receipts and payments.

12


     5. Change Control

        Procedures should be developed and responsibility
        assigned for identifying, evaluating, and accommodating
        changes that may occur during project design and
        construction.  Procedures should be clear, should
        permit results to be achieved rapidly, and should
        provide for full evaluation of the impact of the
        changes.  The avoidance of changes and the prompt
        settlement of change orders and  potential or actual
        claims must be emphasized. Judicious delegation of
        monetary authority to approve change orders at the
        field level can expedite this process.  A mechanism
        should be provided for timely resolution of claims (See
        also, section F, Dispute Resolution )

D. HUMAN RESOURCE AND LABOR RELATIONS POLICY

   It is essential that human resource factors be considered in
   both initial project development and project execution.
   Human resource considerations include all elements that are
   related to the recruitment, selection, and utilization of
   all levels of personnel under a coordinated and planned
   administrative procedure. Human resource considerations that
   can have an impact on the project even though they do not
   deal directly with employment of personnel at the project
   also should be considered.

   1. Statutory and Regulatory Requirements

      Federal, state, and local statutory requirements should
      be identified and incorporated in administrative
      procedures.  Consideration should be given and reference
      should be made to wage and hour requirements and
      compliance with state and local regulations and equal
      employment opportunity regulations (including a local
      plan if one exists).  In addition, potential federal,
      state and local labor legislation (e.g., right--to-work
      and common situs laws,  changes in the Taft-Hartley Act,
      and Workmen's Compensation) that could have an impact on
      project development should be identified and referenceed.


   2. Labor Relationsd.

      An assessment should be made of prevailing labor
      practices and conditions. Policy should be established
      with regard to the factors listed below, and
      responsibility should be assigned accordingly.

      a. Use of Union or Open Shop

         It must be decided whether organized labor or open
         shop labor will be used as well as whether this
         decision can be left as a discretionary matter for the
         construction phase.

l3


     b. Use of Locally Negotiated Labor Agreements or Project
        Agreements


        It must be decided whether locally negotiated
        agreements or project agreements should be used if
        organized labor is employed.  Where building trades
        have been well organized, local agreements have a
        history of being effectively managed and a cooperative
        relationship has existed between collective bargaining
        parties.  Where building trades are well organized but
        on an individual craft basis and contractor bargaining
        is more individual and divided by labor agreements
        having different expiration dates, varied hours,
        different holidays and different conditions, a project
        agreement may be most appropriate.  (The project
        agreement's strength is that it provides for uniformity
        of conditions and the elimination of work stoppages and
        presents a uniform  procedure for dispute resolution.)


    3. Local Conditions

       Provision should be made for assessing local community
       and manpower functions to determine advantageous
       relations to be pursued to enhance project development
       (e.g., transportation and parking facilities,
       organizations assisting in minority employment
       opportunities, vocational and manpower training
       programs, panels and groups dealing with employment and
       other human resource concerns).


E. RISK MANAGEMENT

   Risk management implies control of events, and this means
   that events should be anticipated and responded to in
   advance or as they occur.  Procedures should be established
   for   identifying risks, for evaluating the consequences of
   occurrences, for assigning responsibility and
   accountability, and for distributing liabilities.  In
   addition, a program to avoid risk and minimize the
   consequences of occurrences    should be established.
   Consideration should be given to alternate modes of
   insurance, which should be reviewed periodically to assess
   the impact of inflationary pressures.


F. DISPUTE RESOLUTION

   Responsibility should be assigned and procedures clearly
   defined for resolving disputes in a timely manner.  Disputes
   generally should be resolved at the lowest administrative
   level possible.  Among the dispute resolution procedure to
   be considered are litigation, mediation, arbitration, an
   independent board of consultants, and a contract board of
   appeals.  Of course, the best way to deal with disputes is
   to avoid them by mitigating the conditions that cause them.

14


G. Procurement

   1. Policy and Procedures

      General policies and procedures for procurement of
      services, materials, and equipment should be established
      consistent with applicable governmental regulations.
      These should address requests for procurement,
      solicitation, selection criteria for contract award,
      types  of contracts, schedule, price and cost estimates,
      insurance requirements, and special bonding requirements,
      if any.

   2. Negotiation and Administration

      Responsibility and authority should be assigned for
      negotiating and entering into and for administering
      commitments.

   3. Procurement Plan

     A procurement plan should be developed for procurement of
     the major packages of services, materials, and equipment
     that will be sought. The size and content of each package,
     the schedule for delivery, and an estimate of cost should
     be included.


H. DESIGN PROGRAM

   Prior to beginning preliminary design, a program should be
   developed that clearly identifies the organization and key
   personnel responsible for all design functions.  Management
   policies and procedures should be established with respect
   to delegation of review and approval authority for
   controlling design and construction quality and costs and
   for monitoring the schedule.  It must be recognized that
   in public projects consideration should be given to
   sufficient public participation to ensure necessary
   cooperation and to minimize disruptions to the schedule
   (See also, section C.5, Change Control)
        A system should be developed and authority assigned for
    maintaining detailed coordination of individual design
   packages and the total project design.  Procedures should be
   established for maintaining continuous review of all phases
   of design jointly carried out by the owner consultants, and
   operational personnel.


I. REAL ESTATE ACQUISITION AND DISPOSAL PROGRAM

   Responsibility should be assigned for developing a real
   estate program that identifies: (1) required permanent and
   temporary interests in real estate and their purpose in
   relation to the project; (2) required utility and railroad
   easements and re-arrangement agreements; (3) procedures for
   acquisition, development, and disposal of real estate,
   including cost scheduling and funding; and (4) procedures for
   property management.
        A system should be developed for executing the program
   and should include policies and procedures for executing
   such functions as legal

15


   certification, property appraisal, property management,
   relocation assistance for displaced people, demolition or
   disposal of property not required, and scheduling and
   funding  of activities to meet project requirements.

J. COMMUNICATIONS PROGRAM

   A program should be developed and responsibility assigned
   for maintaining communications among all participants,
   affected organizations, and the general public.  The
   communications program should support all project
   functions (e.g., management control, real estate, design,
   construction), should establish policies and procedures for
   reporting project progress, and should include schedules for
   periodic  meetings and reports.


K. CONSTRUCTION PROGRAM

   It is essential that construction concerns be dealt with
   adequately in the design and procurement phases early in
   project development.  A construction program should be
   developed that clearly identifies all major construction
   functions and the organization and key personnel responsible
   for each of these functions.  Management policies should
   be established and procedures developed for delegating
   responsibility and authority for construction management,
   including the handling of change orders and the resolving of
   disputes.  A work plan should be developed and
   responsibility assigned for developing cost estimates
   that are tied to related schedules for all construction work
   packages and for establishing procedures for coordinating,
   monitoring, and reporting on construction operations in
   relation to quality, cost, and schedule.


L. LEGAL REQUIREMENTS

   Responsibility should be assigned and procedures and
   channels of communication should be established for
   fulfilling all applicable legal requirements including the
   following:
     1. Permits--Identification of the permits needed, the
   responsible governmental agency, the procedures for liaison,
   the responsibility for filing, and the time required for
   issurance.
     2. Approvals--Identification of each authority involved,
   the procedures for liaison, the nature of approval required,
   and the details of communication and coordination,
     3. Disputes Resolution--Procedures for resolution and
   identification of responsibility and authority at all levels
   of management. (See also, section F, Dispute Resolution.)


M. SAFETY PROGRAM

   A safety program should be established to ensure maximum
   accident prevention  and protection of employees, property,
   and the general public.

16


   Policies and procedures should be developed in compliance
   with federal, state, and local safety and health regulations
   and standards, and specific contract and client obligations
   and facility requirements for safety, first aid, and medical
   attention should be identified clearly.

        Responsibility and authority should be assigned for
   executing the program.  A system should be developed to
   provide for (1) review and approval of enforcement
   procedures; (2) safety orientation and training; (3)
   reporting, investigating, and recordkeeping; (4)
   environmental monitoring to detect and control hazardous
   conditions; and (5) proper documentation of all tests.


N. OPERATION AND MAINTENANCE INTERFACE

   Provision should be made for incorporating operation and
   maintenance concerns in design and construction solutions,
   particularly during the design phase.  Procedures should be
   established to provide for a continuous review of all design
   stages carried out jointly by owners, consultants, and
   operation and maintenance personnel to ensure that the
   final design incorporates those features that are consistent
   with projected operation and maintenance needs and costs.
   Consideration should be given to evaluating economy of
   design, system continuity and safety, reliability, and
   constructability in relation to budgeted construction costs
   and forecast operating costs.


O. COMMUNICATION INTERFACE MANAGEMENT

   The major interfaces at which performance failure could
   result in serious disruption of project continuity or
   efficiency or could prevent timely completion of the project
   should be addressed.  These interfaces exist between the
   companies involved as partnersand under contracts, between
   functional units, between project locations, between project
   phases, between project and governmental regulatory agencies,
   and between private and other public interests.
        To enhance interface management, the following should
   be defined clearly (1) responsibility, authority, and
   accountability at the interfaces between various project
   functions; (2) inputs and outputs in terms of content and
   schedule; and (3) lines and procedures for communication.
   Procedure for communication within the project organization
   should include authorizations, reports, meetings, and
   reviews supported by records management.  Procedures for
   communication with elements external to the project should
   include public relations; applications for permits and
   licenses; and reporting requirements imposed by contracts,
   grants, regulations, and other legal requirements.


P. MAINTENANCE OF THE PLAN

   Responsibility should be assigned to ensure that the
   portions of the management plan incomplete at the time the
   original plan is issued are

17


   completed and that revisions required by changes are made.
   Periodic reviews of the plan should be made to ensure its
   currency and appropriateness.

18


                             APPENDIX
                SURVEY OF LOCAL TRANSIT AUTHORITIES




The Committee contacted 17 local transportation authorities to
determine what methods currently are being used to develop
formal management plans for urban construction work.  The
authorities were asked whether they had a formal management
plan for executing urban construction projects.  If they did,
they were asked to submit a copy and explain when it was
instituted and how staff members and other project participants
are familiarized with it.  If they did not have a formal plan,
they were asked to submit copies of memos, reports, or other
documents used in implementing construction projects.  In
addition, they were asked to submit an organization chart, if
available, that would show the organizational structure and
staffing of the authority, how construction activity was
related to the overall structure, and how responsibility and
authority was delegated among the various personnel.
        Of the 17 authorities surveyed, 11 submitted such
documents as organization charts, functional statements, and
complete planning documents used in funding requests.  Three
indicated that some of the requested information was not
available at the time because the plan was being revised or the
authority was being reorganized.  Two indicated that the
construction function was performed by some other municipal
organization and was not their responsibility. One did not
respond.
        After reviewing the survey responses, the Committee
found that each contained many of the primary elements of a
model comprehensive written project management plan.  One
authority submitted drafts of two relatively comprehensive
procedural manuals, and an application for state funds for
construction of a light rail transit system prepared by
another authority satisfied almost a11 the Committee's criteria
for a model comprehensive written project management plan.
Several other extensive and elaborate documents that included
construction project management procedures also were submitted.
        The Committee also found that the organizations
comprising the transit management authorities of cities vary
greatly in terms of their origins, their responsibilities, and
their methods of operation.  Political factors and
considerations appear to have great influence on metropolitan
transit systems.  This influence becomes particularly

19


complex when systems serve multiple political jurisdictions.
Most transit authorities operate under a board of directors,
and the members, who serve for varying terms, usually are
appointed by some elected official or group of officials (e.g.,
governor, mayor, city council, or a combination of these).  In
some cases, the members may be elected officials from a local
government who bring close political ties to the management
function.
        Each board usually has an executive director or general
manager with a staff reporting to him.  The functions of
planning, design, engineering, and construction usually can be
identified within the staff organization.  Generally, however,
the actual performance of these functions is accomplished under
contract and the board's staff serves in the role of contract
supervisor.  The degree of active participation by the boards
also varies from almost complete reliance on the general
manager and staff to one of close supervision of project
progress.
        One transit authority operates as an administration
under a state department of transportation, and planning for a
construction project originates in a planning and program
development division with an initial funding action, which is
required for inclusion in the governor's budget.  Once approved
by the legislature, the lead role shifts from the planning and
program development division to the rapid transit development
division.  At this point, a project manager assumes
responsibility for management of the project with the support
of contract design and construction managers.  A third
division, the metropolitan transit system division, is
responsible for operations and maintenance and has the greatest
number of employees.  The managers of these divisions and
several of their immediate staff are contract employees, but
all others are state employees.
        In another case, transportation and construction are
separate functions of a city government.  A transportation
department is responsible for operating the city's bus and
rapid transit system, providing traffic engineering, performing
maintenance, and providing for traffic safety while a public
works department is responsible for major construction
projects.  This arrangement prompted the two departments to
formulate a "statement of understanding" that identifies the
powers duties, responsibilities, and functions of each with
respect to construction activities.
        Most of the information received by the Committee
indicates that the design, engineering, and construction
functions are directed by one manager while planning is handled
by another.  Exactly how the planning process is carried out
appears to vary greatly from authority to authority.  In
general, however, extensive coordination between planners and
technical staff  appears to be required, but the technical
staffs usually are small and limited in terms of actual design,
engineering, or construction capability.  Once large-scale
construction projects have been approved and funded, most of
the day-to-day design and construction work is performed under
 contract by engineering and construction firm.
        Although there were many similarities, marked
differences were found in the management approaches reported by
the authorities.  These can be attributed in part to the
varying conditions imposed by legislative requirements under
which authorities operate.

20


REFERENCES

1.  American Society of Civil Enginees, Construction Division,
    Proceedings  of 1979 Conference on Construction Risks and
    Liability Sharing, Vol. 1.

2.  Bay Area Rapid Transit District, Construction Department,
   resident engineer's manual, organization chart, and
    contract and construction management reports.

3.  Robert R.Britney, "Project Management in Costly
    Environments," Project Management    Quarterly (June 1978):
    31-42.

4.  Building Research Advisory Board, Commission on
    Sociotechnical Systems, National Research Council,
    Exploratory Study on Responsibility, Liability, and
    Accountability for Risks in Construction, 1978.

5.  City and County of Honolulu, "Statement of Understanding
    Between Department of Transportation and Department of
    Public Works," October 1977, and organization charts.

6.  D. Brian Harrison, "Owner Oriented Information Systems for
    MultiProject Control," Project Management Quarterly (June
    1978): 27-30.

7.  Gerhard L. Hollander, "Integrated Project Control, The
    Management Concept," Project Management Quarterly (June
    1978): 43-49.

8.  Kenneth A. Kettle, "Proposed Construction Management
    Specification,"Proceedings of the American Society of Civil
    Engineers, Vol. 105, No. CO4, December 1979.

9.  Maryland Mass Transit Administration, "UMTA Third Party
    Contract Standards Certification Request," October 19,
    1979,and "Reorganization of the Mass Transit Administration
    Rapid Transit Development Division," August 1978.

10. Massachusetts Bay Transportation Authority, "Boston Region
    Transportation Improvement Program, 1980-1984,"
    "Transportation Planning in the Boston Region 1979-1980,"
    "Transportation Systems Management Element of the
    Transportation Plan for the Boston Region, (MAPC area)
    Unified Planning Work Program 1980-1984," October 1979, and
    organization charts.

21


11. Metropolitan Atlanta Rapid Transit Authority, "MARTA
    Quality Assurance Program Plan," June 1979.

12. Metropolitan Atlanta Rapid Transit Authority, Engineering
    Report PBTBA-7l-l and organization charts.

13. Metropolitan Dade County Office of Transportation
    Administration, Policies and Procedures Manual for
    Procurement and Construction Management, Stage 1, Rapid
    Transit System (draft) and KTG Construction Management
    Manual, MDC Rapid Transit System (final draft).

14. New York City Transit Authority, "Contract Control Report,
    Capital Program" and organization chart.

15. Henry F. Padgham and Howard J. Chaliff (Parsons,
    Brinckerhoff/ Tudor),"Construction Cost Control During
    Design of Major Transit Systems.

16. Port Authority of Allegheny County, "East Busway
    Construction Schedule, UMTA Project PA-03-0012,"  "Stage
    I-A, Light Rail Transit Construction/Procurement Schedule,
    UMTA Project PA-03-0095," and organization charts.

17. Port Authority of New York and New Jersey, Tenant
    Construction Review Manual,   1979.

18. Portland, Banfield LRT Project Administration,
    organization information.

19. San Diego Metropolitan Area Transit Authority, "Application
    for SCA 15 Funds to Design/Construct San Diego Light Rail
    Transit Project," October 1978.

20. Southern California Edison, Los Angeles Department of Water
    and Power, Department of Energy, California Energy
    Commission, "10 MWe Solar Thermal Central Receiver Pilot
    Plant," Project Management Plan, 40-F-00015, July 1979.

21. Southeastern Pennsylvania Transportation Authority,
    organization chart and function statements.

22. U.S. Atomic Energy Commission, Division of Construction,
    "Management of Construction Projects," AEC Manual Appendix
    6101, November 8, 1974.

23. U.S. Department of Energy, Fast Flux Test Facility Project
    Office, "Full Storage Facility Project Management Plan,"
    Rev. 2, January 1978.

22


24. U.S. Department of Energy, Fuels and Materials Examination
    Facility Project Office, "The Fuels and Materials
    Examination Facility,"   November 1977.

25. U.S. Department of Energy, Oak Ridge Operations Office,
    "Project Management Plan, Gas Centrifuge Enrichment Plant,"
    December 1977.

26. U.S. National Committee on Tunneling Technology,
    Subcommittee on Management of Major Underground
    Construction Projects, National Research Council, Better
    Management of Major Underground Construction Projects,1978.

27. U.S. National Committee on Tunneling Technology, National
    Research Council, Better Contracting for Underground
    Construction, 1974.

28. Washington Metropolitan Area Transit Authority,
    "Coordinated Safety Program and Reporting Procedures,"
    "Organization Manual FY 1980," "Procurement Policies and
    Procedures Manual," Contract No. 17526L CY 1979 with
    Bechtel Associates, Contract No. 37323Q CY 1980 with Harry
    Reese and Associates, Contract No. 37624P CY 1980 with
    DeLeuw, Cather and Company, Appendix A of Design Contract
    No. 3A0162 and "Construction Management of Washington
    Metro".

23/24

(mucp.html)
Jump To Top